    Default Puzzle - Men and Boys

    12 men and 18 boys, working 7.5 hrs per day can do a piece of work in 60 days.
    If one man work is 2 boys work, how many boys are required to help 21 men to do piece of work in 50 days working 9.5 hrs per day.

    Pls give quick answer, its very simple.


  2. #2
    PolicyWala Member
    Join Date
    Oct 2009
    Location
    India
    Posts
    18

    Default

    Work is already finished, so no one is required.

  3. #3
    Super Moderator PolicyWala's Avatar
    Join Date
    Feb 2009
    Location
    New Delhi
    Posts
    675

    Default

    Very Quick. Wait for others answers.

  4. #4
    PolicyWala NewBie
    Join Date
    Sep 2009
    Location
    India
    Posts
    21

    Default

    No one required. Please announce the winner

  5. #5
    NewBie
    Join Date
    May 2009
    Location
    India
    Posts
    14

    Default

    Work is finished, so no one required now.

  6. #6
    Super Moderator PolicyWala's Avatar
    Join Date
    Feb 2009
    Location
    New Delhi
    Posts
    675

    Default

    Thank you all for participating. Yes, you all are right and winner of this puzzle.